NOTE: ARTICLE ARCHIVED AS IS ON THE DAY OF ORIGINAL POSTING FROM CITYOFCAMAS.US
See drone footage at https://vimeo.com/417658306/dc28fa540f. Over the last four weeks, contractors have completed several steps to lay the foundation for the rest of the project, including:
> Clearing and preparing the grade, which creates a level base for roundabout construction.
> Building a retaining wall on the west side of NE Everett Street, to accommodate road widening.
> Starting storm sewer improvements on NE Everett Street, beginning at the south end.
> Removing all previously identified trees and undergrowth (the stumps will be ground out later). Some trees, root wads, and logs, which will be used for landscape features and wood benches.
> Reassessing the chestnut tree, which is still healthy and strong despite the natural lean it has developed over the years.
> Performing minor pruning of the chestnut tree and ivy removal from its trunk to promote new vigor.
NEXT STEPS: During the end of May and into June, underground utilities will be relocated, and new asphalt will be placed to accommodate traffic as roundabout construction begins. **For more on the project, visit the project page any time: www.cityofcamas.us/lakeroadconstruction